Fitting assembly

Assembly procedure with coupling and nut

Direct Assembly
  • Simple procedure for single assemblies of small dimensions
  • Not economic for series assembly
  • Tube ø30,35,38 and 42mm must be pre-assembled in vice
  • Stainless steel connection have to be assembled using per-assembly tool (VOMO)
Process 03
Process 03
Process 03

Lubricate thread and Cone / Nut and Ferrule

Process 10
  • Assemble fitting until wrench - tight(without spanner extension)
  • Mark position of nut
Process 9
Assemble check:
  • Loosen nut
  • Check to make sure that a visible collar covers the front of the first cutting edge
  • It does not matter if the ring can be rotated on the tube -end
Process 8
  • Tighten the Nut around 1 1/4 and 1 1/2 round (Note: Tube must not rotate)
Process 11
  • Then tighten fitting firmly by 30°(1/2flat)
  • Recommended to use spanner extension for sizes over 20mm O.D (see chart)
Process 11
SPANNER LENGTH
Size Spanner Length H (mm)
22-L400
28-L 20-S500
35-L 25-S800
42-L 30-S1000
        38-S1200